UA1000224_Introduction of Energy Efficiency Measures at OJSC “Enakievo Metallurgical Works”


UA1000224: Introduction of Energy Efficiency Measures at OJSC “Enakievo Metallurgical Works”
Last updated 18.03.2013
ITL project ID UA1000224
Project title Introduction of Energy Efficiency Measures at OJSC “Enakievo Metallurgical Works”
Project location Enakievo town of the Donetsk Region of Ukraine
Host Party Ukraine
Other Party Netherlands 
Type of Project  
Fee to be paid  
Sectoral scope(s) 1: Energy industries (renewable/non-renewable sources)
3: Energy demand
9: Metal production
"Track" 1
LULUCF project No
Total Emission reductions expected 2470498.0 t CO2 equivalent
Crediting period 01 Jan 2008 - 31 Dec 2012
Project information provided by host Party The National Environmental Investment Agency of Ukraine has confirmed this JI project under Track 1 procedure by the Order No. 20 dated February 25, 2011 
External link(s) to project information: http://ji.unfccc.int/JIITLProject/DB/FX1G65CCXNL6DMJKCKODRF3QL2Z3EF/details
Current status of the project Operational

 

Назва файлу Опис Дата
 1. UA1000224APRNET08092010EN.pdf Approval Netherlands 08.09.2010
 2. UA1000224APRUKR26012010UA.pdf Approval Ukraine 26.01.2010
 3. UA1000224DET27072010EN.pdf Determination Report (English language) 27.07.2010
 4. UA1000224DET27072010UA.pdf Determination report (Ukrainian language) 27.07.2010
 5. UA1000224MON03122012EN_01042011-31102012.pdf Monitoring report - period 01.04.2011-31.10.2012 (English language) 03.12.2012
 6. UA1000224MON03122012UA_01042011-31102012.pdf Monitoring report - period 01.04.2011-31.10.2012 (Ukrainian language) 03.12.2012
 7. UA1000224MON22012011EN_01012008-30062010.pdf Monitoring report - period 01.01.2008-30.06.2010 (English language) 22.01.2011
 8. UA1000224MON22012011UA_01012008-30062010.pdf Monitoring report - period 01.01.2008-30.06.2010 (Ukrainian language) 22.01.2011
 9. UA1000224MON30092011EN_01072010-31032011.pdf Monitoring report - period 01.07.2010-31.03.2011 (English language) 30.09.2011
 10. UA1000224MON30092011UA_01072010-31032011.pdf Monitoring report - period 01.07.2010-31.03.2011 (Ukrainian language) 30.09.2011
 11. UA1000224PDD14072010EN.pdf Project Design Document (English Language) 14.07.2010
 12. UA1000224PDD14072010UA.pdf Project Design Document (Ukrainian Language) 14.07.2010
 13. UA1000224VER03102011EN_01072010-31032011.pdf Verification report - period 01.07.2010-31.03.2011 (English language) 03.10.2011
 14. UA1000224VER03102011UA_01072010-31032011.pdf Verification report - period 01.07.2010-31.03.2011 (Ukrainian language) 03.10.2011
 15. UA1000224VER13022011EN_01012008-30062010.pdf Verification report - period 01.01.2008-30.06.2010 (English language) 13.02.2011
 16. UA1000224VER13022011UA_01012008-30062010.pdf Verification report - period 01.01.2008-30.06.2010 (Ukrainian language) 03.10.2011
 17. UA1000224VER20122012EN_01042011-31102012.pdf Verification report - period 01.04.2011-31.10.2012 (English language) 20.12.2012
 18. UA1000224VER20122012UA_01042011-31102012.pdf Verification report - period 01.04.2011-31.10.2012 (Ukrainian language) 20.12.2012



-POLL-

Commitment Period

(1)-2008-2012

Assigned Ammount Units  -

 4 604 184 663 t CO2-eqv

Commitment Period Reserve -

2 013 329 750 t CO2-eqv